Designing State-of-the-Art Operating Rooms for a Hospital

Carle BroMenn Medical Center : Normal, Illinois

PROJECT SIZE & COST

4,200 square feet | $2 million

THE CHALLENGE

Carle BroMenn Medical Center needed to renovate and upgrade their existing operating rooms. However, the renovations could not be done all at one time, because the hospital could not afford complete downtime of their operating rooms. The project also included pre-engineered boom ceiling systems, requiring engineering system designs around the specific, pre-purchased equipment. Additionally, the operating rooms needed to be brought up to code.

 

KED SOLUTION : Project Phasing for Continued Operation
All operating rooms were brought up to current code require-ments, with a phasing schedule of two OR room renovations at one time. We incorporated the pre-purchased equipment into our designs, accommodating the specific boom ceiling systems’ needs. As a result, Carle BroMenn Medical Center now has eight, fully updated operating rooms, complete with upgraded boom ceiling systems, and spaces that meet the most current code requirements. These operating rooms were renovated without downtime, ensuring the hospital could continue serving its’ patients throughout the duration project.

ENGINEERING SERVICES PROVIDED
  • Electrical
  • Fire Alarm
  • Fire Protection
  • HVAC
  • Lighting
  • Mechanical
  • Medical Gas Delivery
  • Plumbing